Major Project Updates for the Month of October 2019

Information & Updates

Major Project Updates for the Month of October 2019

A monthly update of recently added, under construction, and completed projects in the Alberta Major Projects Inventory.

Recently Added

23 projects were recently added with a combined value of $1.3B for the month of October 2019

Rattlesnake Ridge Wind Project - https://majorprojects.alberta.ca/details/Rattlesnake-Ridge-Wind-Project/3933
The project involves the construction of 28 wind turbines on Rattlesnake Ridge, southwest of Medicine Hat. Upon completion, the 117.6 Mw wind farm will be able to power up to 79,000 homes.

The location provided on the map is approximate.

Kaybob South #3 Cogeneration Plant - https://majorprojects.alberta.ca/details/Kaybob-South-3-Cogeneration-Plant/3927
The project will see the construction of a high efficiency 40 MW cogeneration plant at the Kaybob South #3 Sour Gas Processing Plant in Greenview County. TransAlta will construct the cogeneration plant which will be jointly owned, operated and [Read More]

Marten Hills Pipeline System - https://majorprojects.alberta.ca/details/Marten-Hills-Pipeline-System/3935
The Marten Hills Pipeline System consists of a new crude oil and condensate pipelines near Slave Lake, Alberta. The system will run 85km and terminate at an interconnection point with the Plains Midstream Rainbow pipeline system, which serves the [Read More]

Bonnybrook WWTP Cogeneration Expansion - https://majorprojects.alberta.ca/details/Bonnybrook-WWTP-Cogeneration-Expansion/3946
Upgrade and expansion of the Bonnybrooks Waste Water Treatment Plant's existing Power Generation and Heating facility, including a building addition, new 4MW combustion turbine generator, new 1MW steam turbine generator, new steam boilers, new fuel [Read More]

Dominion Apartment Complex - https://majorprojects.alberta.ca/details/Dominion-Apartment-Complex/3926
Construction of the dominion apartment complex will involve two 15-storey towers located in Calgary's Bridgelands neighbourhood. Each tower will contain approximately 150 units.

Rangeview Sanitary Trunk Project - Phase 1 - https://majorprojects.alberta.ca/details/Rangeview-Sanitary-Trunk-Project-Phase-1/3931
The Rangeview Sanitary Trunk is a greenfield 1800 mm concrete gravity sewer from a chamber in Cranston, crossing under Deerfoot Trail and running along 210 Ave. SE. The project includes 121 m of open cut, 3450 m of micro-tunneling installed pipe, [Read More]

Alt Hotel - University District - https://majorprojects.alberta.ca/details/Alt-Hotel-University-District/3947
The Alt Hotel is a new hotel under construction in Calgary's University District. The 15 storey hotel will feature 156 rooms, retail space at ground level, and an underground parkade.

A building permit was issued for the project on October 28, [Read More]

Goodwin at Belmont Townhomes - https://majorprojects.alberta.ca/details/Goodwin-at-Belmont-Townhomes/3943
Three-story, 178 units phased development featuring two and three bedroom townhomes located in southeast Calgary

Stettler Grain Terminal - https://majorprojects.alberta.ca/details/Stettler-Grain-Terminal/3925
Construction of a new 42,000 tonne grain terminal in Stettler, than is located on the CP Rail line. A railway loop track will be built that can accommodate a 150-car unit train. Construction is expected to be complete in 2020.

Apex 2 Warehouse Distribution Centre - https://majorprojects.alberta.ca/details/Apex-2-Warehouse-Distribution-Centre/3928
The project will see a new warehouse distribution centre built in Northwest Edmonton's Mistatim Industrial Area at 14010 164 Street. The warehouse will measure approximately 316,700 square feet.

A building permit was issued on October 8, 2019 [Read More]

Roozen Family Hospice Centre - https://majorprojects.alberta.ca/details/Roozen-Family-Hospice-Centre/3942
A hospice care facility will be built at 9808 - 148 Street in the Crestwood neighbourhood in west Edmonton. The facility will support a maximum of 12 residents. A building permit was issued on October 22, 2019.

Milner Building Residential Conversion - https://majorprojects.alberta.ca/details/Milner-Building-Residential-Conversion/3939
The project will convert the 12 storey Milner commercial building into a residential apartment complex that will feature an estimated 200 apartment units, with retail along the ground level.

Apex 1 Warehouse Distribution Centre - https://majorprojects.alberta.ca/details/Apex-1-Warehouse-Distribution-Centre/3941
The project will see a new warehouse distribution centre built in Northwest Edmonton's Mistatim Industrial Area at 16910-140 Avenue. The warehouse will measure approximately 216,900 square feet.

A building permit was issued on October 22, 2019 [Read More]

Muttart Conservatory Modernization - https://majorprojects.alberta.ca/details/Muttart-Conservatory-Modernization/3944
This project is to construct exterior and interior alterations to the Muttart Conservatory. The modernization project will take 18 months to complete.

A building permit was issued on October 23, 2019.

Regatta at Auburn Bay - https://majorprojects.alberta.ca/details/Regatta-at-Auburn-Bay/3932
The scope includes a 4 storey condo complex in the Auburn Bay neighbourhood in Calgary. The 48 condos range from 552 to 1,028 square feet and will be completed in the first half of 2021.

Landmark Movie Theatre - Tamarack - https://majorprojects.alberta.ca/details/Landmark-Movie-Theatre-Tamarack/3940
Landmark will be constructing an 8 plex cinema in the Tamarack neighbourhood of Edmonton. A building permit was issued for the cinema on October 21, 2019.

Stonehaven Apartments - Phase 2 - https://majorprojects.alberta.ca/details/Stonehaven-Apartments-Phase-2/3938
Construction of an apartment building on top of an existing parkade in the Walker neighbourhood of south Edmonton. The apartment will have 48 units upon completion.

A building permit was issued for the project on October 21, 2019.

Canada Post Calgary Office Expansion - https://majorprojects.alberta.ca/details/Canada-Post-Calgary-Office-Expansion/3930
The project will create additional office space at the Canada Post distribution centre located in Northeast Calgary (2777 Sunridge Boulevard NE).

A building permit was issued for the project on October 9, 2019.

Bear Street Shared Street Reconstruction - https://majorprojects.alberta.ca/details/Bear-Street-Shared-Street-Reconstruction/3934
The project will work on street beautification, implement traffic calming measures, and create a barrier-free street so cyclists, pedestrians, and vehicles can share the road equally.

Banff issued an RFP for the project Oct 10, 2019.

103 Street Centre Lobby Renovation - https://majorprojects.alberta.ca/details/103-Street-Centre-Lobby-Renovation/3929
The project aims to modernize the 103 Street Centre in downtown Edmonton. The scope includes renovations to the lobby, main floor washrooms, fitness centre, conference centre, and tenant lounge.

A building permit was issued for the project on [Read More]

Seafood City Supermarket Fit Up - https://majorprojects.alberta.ca/details/Seafood-City-Supermarket-Fit-Up/3945
The project includes interior alteration to a tenant build-out of an existing vacant retail space. The Sea Food City Supermarket will occupy the space previously occupied by Home Outfitters.

Alberta Industrial Heartland Waterline Loop - https://majorprojects.alberta.ca/details/Alberta-Industrial-Heartland-Waterline-Loop/3936
Plans call for the construction of a new 450mm waterline to loop two existing waterlines to provide water to the Northeast Industrial Heartland. The two existing waterlines are known as the Heartland Regional Water Line on the west side and the [Read More]

Under Construction

11 projects with a combined value of $5.1B are now under construction for the month of October 2019

Taza Mixed Use Development - https://majorprojects.alberta.ca/details/Taza-Mixed-Use-Development/3719
The Taza mixed-use development will consist of 1,200 acres of development on the Tsuut’ina Nation (bordering Calgary), which will include 17 million square feet of real estate. There will be three distinct areas of the development known as Taza [Read More]

CapitalCare Norwood Development - https://majorprojects.alberta.ca/details/CapitalCare-Norwood-Development/376
Complex continuing care facility to accommodate up to 350 beds. Includes the renovation of a medical facility (Angus McGugan Pavilion), and the construction of a 40,000 square foot medical centre.

The new 40,000 square metres re-development [Read More]

Points West Living Red Deer Expansion - https://majorprojects.alberta.ca/details/Points-West-Living-Red-Deer-Expansion/3923
Points West Living will add 150 assisted living units (75 long-term care, 75 dementia care) to the north side of its existing 139 unit facility. Project is located at 6950 Taylor Drive and is estimated to be complete in 2021.

CX Grandin - https://majorprojects.alberta.ca/details/CX-Grandin/3592
The project involves the construction of a 21 storey, 221 unit residential complex in the Grandin neighbourhood in Edmonton.

The View Residential Tower - https://majorprojects.alberta.ca/details/The-View-Residential-Tower/3951
The project involves the construction of a 23 storey tower that will contain 178 residential suites in the Grandin neighbourhood, in central Edmonton. The tower is estimated to reach 249ft in height upon completion.

Templemont Affordable Housing - https://majorprojects.alberta.ca/details/Templemont-Affordable-Housing/3948
The project will build the Templemont Affordable Housing Project in Calgary's northeast on the site of the former Temple Anglican Church. The project will contain 120 units (70 for supportive living and 50 for seniors with low income).

Chappelle East K-9 School - https://majorprojects.alberta.ca/details/Chappelle-East-K-9-School/3827
Construction of a new K-9 school in Chappelle East. Location is yet to be determined.

Calgary Bobsled & Luge Track Renovation - https://majorprojects.alberta.ca/details/Calgary-Bobsled-Luge-Track-Renovation/3456
The project consists of renovating the refrigeration system, removal of 72 meters of track, and renewal of the remaining section of track which is 30+ years old and is at the end of its lifespan.

On October 10, 2019, Winsport proceeded with the [Read More]

Shepard Station Suburban Office Campus Building 1 - https://majorprojects.alberta.ca/details/Shepard-Station-Suburban-Office-Campus-Building-1/11
The Shepard Suburban Office Campus is a 33-acre site which will house 850,000 square feet of office development. Building #1 includes a four-storey class “A” building comprised of 85,000 ft2 of leasable space. Construction began in late 2019.

The Rise in the Parks of Harvest Hills - Building 16 - https://majorprojects.alberta.ca/details/The-Rise-in-the-Parks-of-Harvest-Hills-Building-16/3949
The project involves the construction of building #16 of The Rise in the Parks of Harvest Hills. This project is creating a new townhome complex near the Deerfoot Trail in north Calgary.

A building permit was issued on October 30, 2019.

The Strathcona Hotel Redevelopment - https://majorprojects.alberta.ca/details/The-Stratcona-Hotel-Redevelopment/3950
The project will redevelop one of Edmonton's oldest buildings, the Strathcona Hotel which was built in 1891. The project will contain office and retail space while modernizing the building and preserving all heritage elements.

A fire started in [Read More]

Completed

12 projects with a combined value of $3.3B have been completed for the month of October 2019

Christina Lake Thermal Expansion Project - https://majorprojects.alberta.ca/details/Christina-Lake-Thermal-Expansion-Project/555
Phase G of the Christina Lake expansion was halted in early 2015 due to market conditions but has been restarted in Q1 2017. First oil is expected in late 2019. Phase G carries a capital cost of $950M

The expansion would increase the facility's [Read More]

Frozen Potato Processing Plant - https://majorprojects.alberta.ca/details/Frozen-Potato-Processing-Plant/3397
Project is the largest private investment in Lethbridge history. The potato processing plant will be able to handle 15,000 acres of potato crop annually. This project will create 400 construction jobs, and support up to 190 full time jobs upon [Read More]

Bassano Dam Upgrades - https://majorprojects.alberta.ca/details/Bassano-Dam-Upgrades/138
Construction of a cast in place concrete spillway to at the Bassano Dam. The new spillway will be able to handle 70% more water flow than what was experienced during the Southern Alberta floods in 2013.

E11even - Harley Court Apartments Conversion - https://majorprojects.alberta.ca/details/E11even-Harley-Court-Apartments-Conversion/3465
Conversion of a 15 story office tower, known as Harley Court into a 177 unit apartment complex featuring 1 & 2 bedroom units. Development is known as E11even.

Protective Service Building Expansion - https://majorprojects.alberta.ca/details/Protective-Service-Building-Expansion/3400
Construction of a new 53,000 square foot $27M RCMP detachment to serve both Spruce Grove and Stoney Plain.

Baytex Energy Centre (Peace Regional Recreation Centre) - https://majorprojects.alberta.ca/details/Baytex-Energy-Centre-Peace-Regional-Recreation-Centre/3345
The Peace Regional Recreation Centre will contain one NHL sized rink, one multi-use field house, a three lane walking track, a fitness room, three multipurpose community rooms, and an indoor children’s play space.

Roadwork - 183294 - https://majorprojects.alberta.ca/details/Roadwork-183294/3732
Details outside the paving and repair of Highway 22 north of Drayton Valley to Highway 16. There will also be intersection improvements to the Hwy 22/16 interchange, including street lights.

City Hall and Churchill Square Upgrades - https://majorprojects.alberta.ca/details/City-Hall-and-Churchill-Square-Upgrades/3334
The project will renovate Churchill square, and open a new fountain/skating rink in front of the building on the former pool site.

Roadwork - 18862 - https://majorprojects.alberta.ca/details/Roadwork-18862/3899
The project will rehabilitate Highway 43 between Whitecourt and Mayerthorpe.

Metis Crossing Cultural Center - https://majorprojects.alberta.ca/details/Metis-Crossing-Cultural-Center/3880
The new Metis Crossing Cultural Center will provide 10,000 ft2 of gathering spaces, meeting rooms, classrooms, exhibits and interpretive spaces to engage visitors on metis culture and history.

MANASC ISAAC are the Architects for the project.

Roadwork - 20534 - https://majorprojects.alberta.ca/details/Roadwork-20534/3869
Roadwork to repave a section of Highway 670 from east of Highway 749 to Highway 750.

Belgravia Square - https://majorprojects.alberta.ca/details/Belgravia-Square/3845
The project consists of a four storey apartment complex in the Belgravia neighbourhood of Edmonton. The complex will feature 69 units when complete.

Contact

For questions about the Major Project Updates, please contact majorprojects@gov.ab.ca